Update Week 4
Feaker has relayed all the sanitary main and structures on Lynch Ave. The only 8” watermain remaining to install are the two bends and the short section connecting them at the west end of Lynch Ave. The two 10” tie-ins still need to be completed at Lynch and Hershman; along with the hydrant. The new 8” watermain east of Hershman Ave has passed all the testing, and Feaker is intending to connect the services to the new main starting Monday. They also intend to finish the watermain on the west end, so they can load and sanitize on Monday. Jordan has been in contact with Lumen and the overhead lines and old poles should be removed today and Monday.