Feaker fnished the utilities this week. This includes abandoning storm sewer and removing structures. Feaker is scheduled to remove their equipment on Tuesday, July 5, 2022.
Peter’s Concrete Co. is scheduled to start road and driveway excavation on Thursday, July 7, 2022. With the construction activities of roadway and driveway excavation, expect delays and the possible need for a new route to your destination. There may also be a need for a property owner to park overnight on the road depending on where the contractor has stopped for the day. Peter’s Concrete Co. will try to accommodate the property owners as much as they can to limit the number of disruptions.