Hager Road, South Wall Street, Grand Avenue update

The final grading should be completed tonight; if not early tomorrow. NEA may pave some driveway sections this week. There are no changes to the traffic control, but the castings and valves are now 6” above the gravel grade. There are barrels covering them, but damage to the structure, valve and/or vehicle could occur if they are struck. The driveways are ramped, but the remainder of the gutter is also a 6” lip. There may also be heavy machinery moving about the project area, so avoid this area if possible.