Please ensure Javascript is enabled for purposes of website accessibility

2024 Road Construction North Wall-Danish Way

Please be aware that there may be temporary interruptions in traffic flow at the intersection of North Avenue and North Wall Street during road construction.

North Avenue Update

Kruczek has completed the storm sewer on North Ave east of N. Wall St. The remainder of this week and all next week will consist of road construction. The current plan is to work on excavating one lane starting at N. Wall St heading east to the project limits with trucking coming from N. Wall St, not Maribel Rd. Let me know if you have any questions or concerns.

 

 

North Avenue/Danish Way updates to date, July 3, 2024

Here are the updates to date. The 12" water main extension to the east of N. Wall St has been completed and pressure tested. The storm sewer will be approximately 90% completed east of N. Wall St after today. Areas of the intersection are scheduled to be excavated starting next week with a flagger on site. Excavation of the roadway to subgrade east of N. Wall St will also begin next week. The contractor is aware of the Thursday night event at The Rod and Gun Club, so the lot will be accessible. If you have any questions or concerns please let me know.

  • Kruczek is going to be working in the intersection of Wall Street and North Ave on Monday.  It will be down to 1 lane traffic for North Avenue and Wall street.  Kruczek is planning on having a flagger there during the lane closures.
  • Kruczek will be starting on roadway excavation next week which will include the removal of existing material down to subgrade and placing stone for the new roadway starting on the East side of the Wall Street intersection with North Avenue and will continue to the Eastern project limits.

 

Temporary mailbox location during North Avenue/Danish Way road construction

 

The Village of Denmark 2024 Street and Utility project is expected to begin in early June with an anticipated completion in late August 2024. Below is a link to the details presented in the Public Information Meeting on May 6th.  Please check back here for more information and the progress of the project.

Public Information Meeting North Avenue-Danish Way Construction Project

Pre-Construction Schedule

North Avenue Reconstruction Overall Project Site

Questions and Answers regarding construction:

Q & A (Questions in Red, Engineer response in Black)  

Q: We shoot every Thursday night starting at 6pm will the club’s driveways be open either one or both so our members have access?

A: One driveway will be closed at a time. Access will be provided at all times except when crews are working directly in front of driveway locations. Any long-term access change will be communicated by the contractor 24 hrs in advance. Driveway closures will occur during curb and gutter, concrete driveway approach and sidewalk work, the closures will be limited to a maximum timeframe of approximately 4 weeks. Construction will be staged so that driveways are closed on one side of the road at a time.

Q: Will there be any cost or expense billed to the club for any of this improvement to the roadway?

A: No. The only exception would be if lead water services are found to be present. The Village does not have any records indicating that lead water services exist within the project limits.

 Q: I am assuming there will be power & sewer shut offs during part of this construction we would just need to know if will affect our Thursday league shoots?

A: No anticipated power shut-offs during construction. Sewer service will be maintained during construction.

Q: Any dates that the road will be closed off that we will not have access to the club?  Need to know so if we need to cancel a week of trap.

A: No full closures are anticipated.

Q: Some on the board wanted to know if there was a site map of the construction available? 

A: We can provide plan sheets showing the limits of the project.

 Q: The roadway will be widened after construction completed correct? If so will there be any parking available on the new road?

A: North Avenue will be widened and curb and gutter will be added. Parking will not be permitted on the road.

 

Contact information for questions during construction project

Onsite Engineering Technician – McMahon Associates Inc.

Tim Verhagen

920-740-3050 cell

[email protected]